Fayetteville Policies and Procedures 705.0
Construction--Time Allowances for Initiation of Construction
Major campus construction and renovation projects that require a method of financing form fall in this procedure. Projects done by Facilities Management would be exempt from many of these procedures; therefore, do not consider this policy applicable for minor office renovations.
The following table will give you an idea of what time allowances should be considered when planning major construction projects:
1. Review of construction bid documents a. State Fire Marshal
b. State Health Department c. Facilities Management d. Facilities Planning |
2 weeks |
2. Advertisement of bids | 3 weeks |
3. Bid review and award a. Bonds checked
b. Insurances checked c. Comparisons made |
1 week |
4. Execution of contracts and purchase orders a. Contract preparations
b. Purchase order preparations c. Contracts sent to UA System Office d. Legislature approval of contracts |
5 weeks |
5. Preconstruction meeting | 1 week |
6. Initiation of construction | 2 weeks |
Total time | 14 weeks (3 1/2 months) |
---|